Monte Vista Elementary School, Interm Portable Housing
* Bids are due June 2, 2022 at 10:00AM
This project consists of the following:
Relocation of (4) Existing Portable Classrooms, Installation of Prefabricated Ramps & Landings, Temp Power / Comm / Data to buildings, stand alone fire alarm system
Plans can be obtained on Smartbid or the following link:
https://schipperconstruction.box.com/s/7kkuxqifxj2akcxbnke10j4jix1hs82a
If you have trouble accessing the files, please contact us at info@schipperconstruction.com. We will have a hard copy set of plans in our plan room
This project IS PREVAILING WAGE. Please include your DIR Number when submitting your bid
MBW / WBE / DVBE Contractors are encouraged to bid
FSCC Estimator: Erwin Villegas erwin@schipperconstruction.com
SCOPE OF WORK:
The scope of work includes selective demolition, portable building relocation, abatement, site clearing, site grading, SWPPP, asphalt paving, chain link fencing, signage, electrical & fire alarm.